Update on the 2020 Paving Program
- Willow Road Phase 1 (between Amwell Road & Valinor Drive) is completed
- Andria Avenue is completed
- Hillsborough Road (between Bypass & Willow Rd) is completed
- Brooks Boulevard – concrete ramps are completed
- Willow Road Phase 2 (between Valinor & Hillsborough Rd) is under NJDOT review, paving planned for Fall 2020 or Spring 2021
- Paving of Brooks Boulevard, East Mountain Road, Wertsville Road, and the Green Hills Development should be completed by the end of June
- Camplain Road has been held up due to work by PSE&G